What's actually in the trench
A typical ground-mount-to-house trench runs:
- 2–4 inch conduit — usually Schedule 40 PVC for direct-bury, or rigid metal conduit (RMC) where required by AHJ
- 3+ wires: two phase conductors + ground (residential) or three phase + ground (large commercial)
- Optional: monitoring conduit — data cable for inverter communication if not using cellular/WiFi
- Underground warning tape — required ~12 inches above conduit by NEC 300.5
- Concrete encasement in some jurisdictions for shallower runs
Trench depth requirements (NEC 300.5)
| Conditions | Direct burial cable | PVC conduit | Rigid metal conduit (RMC) |
|---|---|---|---|
| Under residential lawn / garden | 24" | 18" | 6" |
| Under driveway (residential) | 18" + concrete | 18" + concrete | 18" |
| Under commercial parking | 24" + concrete | 24" | 24" |
| Under street / public roadway | 30" | 30" | 24" |
Why ground-mount trenches are so expensive
- Excavation labor. 100–200 feet of trench at 18–24" depth is 5–15 cubic yards of dirt. At $80–$150/hour for a mini-excavator + operator, plus hand-finishing around obstacles, plus tree-root navigation — easily $1,500–$4,000 in excavation alone.
- Conduit + wire. 200 feet of 2" PVC + #1/0 AL or #4 CU conductors + ground = $400–$1,200 in materials.
- Concrete encasement if AHJ requires it (~$300–$800).
- Restoration. Re-grading, re-seeding, replacing landscape rocks, fixing irrigation lines — $500–$2,000.
- Permit and inspection. Electrical underground inspection (open trench), then re-inspection after fill.
- Voltage drop sizing. Long runs require larger conductors to keep voltage drop under 2%. A 200-foot run at 30A often needs #1/0 wire vs #4 for short runs — conductor cost roughly doubles.
Total: a 100-foot trench typically runs $3,500–$8,000 added to system cost. 200 feet runs $6,000–$15,000. For long-distance runs (500+ feet from a barn / shed solar to the main house), trenching can easily exceed $20,000.
Overhead alternative
For longer distances, overhead wire on poles or strung between fixed structures (existing poles, barn-to-house) can be 30–60% cheaper. Pros and cons:
| Aspect | Trenched (buried) | Overhead |
|---|---|---|
| Cost (200 ft) | $6,000–$15,000 | $2,500–$6,000 |
| Aesthetics | Invisible | Visible — wires + poles |
| Vulnerability | Frost-protected, animal-protected (with concrete) | Wind / ice / falling-tree damage |
| Code restrictions | NEC 300.5 trench depth | NEC 225 + 230 height/clearance + AHJ pole spec |
| Lifespan | 40+ years (PVC conduit) | 20–30 years (UV/ice exposed) |
| Inspections | Open trench + buried | Pole installation + clearance |
| Future maintenance | Hard to access | Easy to inspect/repair |
Overhead is most common for rural ground-mount systems (barns, sheds, free-standing arrays where the path between the array and the house is long and trees aren't blocking).
Aerial messenger cable (in between)
A middle option: aerial messenger cable strung on existing utility-grade poles. Used commonly by farmers running solar from a remote barn to the meter. Roughly 50–70% the cost of trenching. Requires AHJ approval and proper pole anchoring.
Cost-saving tips
- Trench during other excavation. If you're already digging for landscape, irrigation, or septic work, adding a solar conduit run is incremental cost — not a separate $5,000 project.
- Run extra conduit. While the trench is open, run a 1” spare conduit alongside. Cheap insurance for a future EV charger run, monitoring upgrade, irrigation control wiring.
- Use directional boring for crossing under driveways without tearing them up — expensive per foot but cheaper than driveway replacement.
- Right-size the conductor. Don't oversize "just in case" if voltage drop math allows the smaller wire.
- Let the homeowner DIY backfill if they have time — saves $500–$1,500 on labor (after the inspector signs off the open trench).
Frequently asked questions
Why is the trench cost on my ground-mount bid so high?
Probably about right if it's 100+ feet to the panel. Long-distance underground conductor runs at 18–24" depth + permit + restoration genuinely cost $4,000–$10,000. If the bid feels high, ask for a line-item breakdown: excavation, materials, restoration, permit, voltage-drop conductor sizing.
Can I dig my own trench to save money?
Sometimes. Some installers will let you provide the open trench (pre-permit-inspection) and they only do the conduit + wire pull + connection. Saves on excavation labor. Risks: if your trench fails inspection (depth, slope, separation from gas line), you re-dig.
What about running solar on existing utility poles?
Generally not allowed without explicit utility approval. Utility-owned poles carry utility-grade infrastructure; the utility doesn't want a homeowner's PV conductor mixed in. Your own poles on your own property are fine subject to AHJ approval.